Featured Projects
FRÁSEC Ventures Corporation delivers high-quality standards across a diverse portfolio, specializing in comprehensive commercial and residential construction as well as aggregates production and supply. From critical structural formworks to massive mining, quarrying, and mineral extraction operations nationwide, we consistently provide the human resources and equipment required to exceed client expectations.
Mining

Philnico Nonoc Nickel Project
Pacific Nickel Philippines Inc.
Nonoc Island, Surigao City, Surigao del Norte
July 2007 – December 2015
Scope of Work
General Contractor (1,500,000 WMT annually)
● Mine nickeliferous ores (laterite overburden, limonite, and saprolite) in the
25,000 hectares mineral reservation
● Sort and extract using backhoes
● Load and haul to the pre-pile yard
● Grade sampling of every truckload in the pre-pile yard
● Pre-stockpiling using wheel loaders
● Haul materials to stockyard
● Stockpiling at stockyard
● Load from stockyard then haul to LCT

PGMC Cagdianao Nickel Project
Platinum Group of Metals Corporation
Cagdianao, Claver, Surigao del Norte
March 2014 – March 2016
Scope of Work
General Contractor (3,000,000 WMT annually)
● Waste Stripping
● Extraction, loading, hauling, stockpiling, beneficiation, rolling, and sun drying
● Barging, ship-loading and direct shipping of nickel ore with over 500 units
equipment fleet and close to 2,000 personnel.

RCBMI Norzagaray Quarry Project
Republic Cement – Norzagaray Plant
Bigte, Norzagaray, Bulacan
June 2012 – March 2024
Scope of Work
Quarrying of Limestone (45,000 MT per month), which includes:
● Drilling and controlled blasting
● Mechanical mining (rock breaking and splitting)
● Extraction, loading, and hauling of limestone from quarry to crusher or
designated stockpile areas
● Material handling
● Pushing and stockpiling of delivered raw materials
● Receiving and stockpiling of rice husk and other alternative fuel

ATN Solar Philippines Rizal Aggregates Project
ATN Philippines Solar Energy Group
Macabud, Montalban, Rizal
January 2018 – September 2019
Scope of Work
Quarrying of basalt (84,000 BCM or 120,000 CUM per month – Waste and Basalt),
including:
● Development and extraction of andesite and basalt materials
● Waste stripping, road development, drilling, blasting, loading, hauling, and
feeding of basalt material to crushing plant and designated stockpile area
● Development and maintenance of environmental protection facilities

MVDM Tawi-tawi Nickel Project
Mina Vida de Mindanao Corporation
Sikulis, Languyan, Tawi-tawi
June 2017 – June 2020
Scope of Work
Subcontractor responsible for:
● Waste stripping
● Extraction, loading, and hauling of nickel ores
● Ship-loading of direct shipping nickel ores
● Road construction and maintenance

Arc Nickel Resources Inc. Banaybanay Nickel Project
Arc Nickel Resources, Inc
Pintatagan, Banaybanay, Davao Oriental
January 2021 – October 2022
Scope of Work
Mine Development, which include construction of:
● Main mine haul and access roads
● Drainage system complete with siltation ponds
● Causeway and waste dumps
● Limonite and Saprolite stockyards and beneficiation yards.
● Saprolite pier yards.
● Environmental erosion & sediment control facilities such as settling ponds
● Motorpool

RCBMI Danao Quarry and Material Handling Project
Republic Cement – Danao Plant
Dunggoan, Danao City, Cebu
June 2012 – June 2023
Scope of Work
Quarrying of Limestone (5,000 MT per month) and Shale (10,000 MT per
month), including:
● Waste stripping, road, and quarry envi infra development
● Extraction, loading, hauling, and crushing, and delivery of
limestone to plant storage.
● Equipment Rental

PACEMCO Cement Quarry Project
Pacific Cement Philippines Inc.
KM 11, Surigao City, Surigao del Norte
January 2009 – May 2014
Scope of Work
General Contractor (25,000 MT per month of Limestone, Silica, and Shale)
● Provide manpower, technical expertise, and equipment for the whole quarry
operations which include drilling, blasting, extracting, loading, and hauling of
limestone, shale, and silica for cement production.
● Mine and road maintenance
● Mine planning and design

Wellex Mining Corp. Libjo Chromite Project
Wellex Mining Corporation
Libjo, Dinagat Island, Surigao del Norte
March 2008
Scope of Work
Joint Venture with 5,000 WMT per month where we are tasked to:
● Mine metallurgical-grade chromite
● Develop roads and mine envi infrastructure

MMDC Cantilan Nickel Project
Marcventures Mining and Development Corp.
Cabangahan, Cantilan, Surigao del Sur
April 2009
Scope of Work
General Contractor (2,000,000 WMT annually)
● Provide mining services from mine development to exploitation.
● Development of mine haul roads, drainage system, siltation
ponds, ore stockyard and waste dumps.
● Extraction, loading, hauling, stockpiling, beneficiation, rolling,
and sun drying, barging, ship-loading and direct shipping of
nickel ore.

Carmen Copper Corp. Concentrate Hauling & Equipment Rental
Carmen Copper Corporation
DAS, Lutupan, Toledo City, Cebu
2008 – 2025
Scope of Work
MAY 2008 – 2021
Contractor tasked with mine development works, such as:
● Dike Construction and Dam improvement
● Mine rehabilitation
● Desilting works
● Mine Drainage construction
● Copper Concentrate Hauling
● Tailings dam construction & improvement
● Road works
FEBRUARY 2021 – JUNE 30, 2025
Hauling of Copper Concentrate (18,000 WMT cu. con per month)
● Transport/hauling of copper concentrate from Carmen Copper
Corp Mill/CarCon area to Sangi Port

Hallmark Mining Corp. Pujada Nickel Project
Hallmark Mining Corporation
Macambol, Mati City, Davao Oriental
November 2015 – Present
Scope of Work
General Contractor for both Alog (November 2015 – Present) and Matayam (May
2025 – Present) areas
● Mine nickeliferous ores (laterite overburden, waste and saprolite)
● Extraction, loading and hauling
● Stockpile management
● Barging and ship loading
● Environmental controls maintenance
● Road development and maintenance
Aggregates

Frásec Iloilo Aggregates (Basalt) Project
Iloilo Aggregates
Libertad, Banate, Iloilo
June 2020 – Present
Scope of Work
●Mountain Quarry w/ drilling and blasting
● Aggregates Crushing and Screening
●Hauling and deliveries of finished products

Frásec Mindoro Occidental Aggregates Project
Min Occ Aggregates
Sta. Lucia, Sablayan, Mindoro Occidental
Upcoming Project – 4th Quarter 2026
Scope of Work
● River Quarry
● Aggregates Crushing and Screening
● Hauling and deliveries of finished products
● Shipment of products using LCT/Barge to neighboring provinces.
Construction

Corona Del Mar Subdivision
Filinvest Development Corporation
Pooc, Talisay City, Cebu
January 1998 – 2002
Scope of Work
● Subcontracting works for Anseca-Acelco Ventures, Inc. in the land development, with the
removal of unsuitable materials.
● Landfilling of an approximate volume of 500,000 m3 of coralline limestone and engineer
● Filling of up to 95% – 100% compaction on a 35-hectare area by the beach.
● Construction of road network, drainage system, water line system, and sewer system
● Phase 1 – Engineered Backfilling of Spine Road to Beach Front (1998 – 2000)
● Phase 2A – Landfilling of blocks at Ph1A and Beachfront Area (2000 – 2001)
● Phase 2B – Land Development of Ph1B, Road Construction of Ph1A and land filling of Staging
Area for Model House (2001 – 2002

Apo Plant
CEMEX Philippines
Tina-an, Naga City, Cebu
January 2002 – February 2005
Scope of Work
● Design & Construction of Empty Bag Transport System
● Road Concreting to APO Port
● Drainage System Construction to Port Area
● Design and Construction of Supply Warehouse
● Construction of APO Haulers Parking Area
● Jetty Platform Construction
● Bad Order Cement Recycling Project
● Plant-wide ACU Maintenance
● Hazard Elimination for
Limestone & Crusher
Conveyor
● Road Pavement and Perimeter
Fence Repairs
● Design and Construction of Oil
& Lubricant Warehouse
● Air Condition – Yearly
Maintenance (2001 & 2002)
● Multi-purpose Building & Site
Development Works
● Multi-purpose Building –
Children’s Playground
● Safety Hazard Elimination
Project
● Design & Construction of
Spare Parts Warehouse
● Improvement of Fire Hydrant
Pump (FM Global)
● Installation of exhaust ducting
at DOPOL Fan
● Construction of Coal &
Gypsum Containment Yard

ATOMED Plant
Taisei Philippines Construction Inc.
Basak, Lapu-Lapu City, Cebu
March – May 2004
Scope of Work
● Site clearing/preparation,
earthworks & soil filling
● Factory building formworks
● Factory rebar works, road
construction of Sinulog Drive
(MEPZ 2)
● Perimeter fencing

Ajinomoto Plant
Taisei Philippines Construction Inc.
Basak, Lapu-Lapu City, Cebu
March – May 2004
Scope of Work
● Pahiyas Drive drainage system
● Construction of roads, curbs,
and gutter
● Perimeter fencing

Celestial Meadows Memorial
Celestial Meadows Developers Corporation
Ward III, Minglanilla, Cebu
Scope of Work
● Land development of a 4-hectare
lot
● Earth-filling with coralline-limestone at 95% compaction
● Construction of road network,
drainage system, and amenities

PAG-IBIG North
ADC Property Ventures Inc.
Fortuna, Mandaue City, Cebu
Scope of Work
● Drainage renovation
● Architectural, Civil & Electrical
works
● Data & Voice Cabling System
● Plumbing & Mechanical works

Fonte Di Versailles
Paramount Property Ventures Inc.
Tulay, Minglanilla, Cebu
Scope of Work
● Earthworks using 175k m3 of
imported backfill materials
● Sidewalks and road construction
● Construction of sewer and
drainage systems
● Perimeter fence
● 400-m boardwalk with wave
dissipation structures

La Cresta Hills
Paramount Property Ventures Inc.
Carcar, Cebu
August 2016 – Present
Scope of Work
● Earthworks
● Road and sidewalk construction
● Construction of drainage and
sewer systems
● Perimeter fence

The Mazari Cove
Paramount Property Ventures Inc.
Inayagan, Naga City, Cebu
June 2020 – Present
Scope of Work
● Road concreting
● Drainage Manhole construction
● Drainage Line System

The Wellington Greens
Paramount Property Ventures Inc.
Cogon, Compostela, Cebu
January 2019 – Present
Scope of Work
● Earthworks
● Road concreting
● Drainage Manhole construction
● Drainage Line System

Legacy Plains Memorial Garden
Celestial Meadows Development Corporation
Toledo City, Cebu
January 2020 – Present
Scope of Work
● Earthworks
● Road concreting
● Blocks Levelling
● Drainage Line System

Celestial Meadows Memorial Garden
Celestial Meadows Development Corporation
Cogon, Compostela, Cebu
April 2019 – Present
Scope of Work
● Earthworks
● Road concreting
● Blocks Levelling
● Drainage Line System
● Icon signage
● Center Road Stamp Crete
● Gate & Guardhouse

Fransesca Highlands
Paramount Property Ventures Inc.
Cadulawan, Minglanilla, Cebu
August 2016 – Present
Scope of Work
● Road construction
● Construction of drainage systems
● Sewer system
● Sidewalks
● Slope protection structures

Provincial Governance Center (Governor’s Hall)
Provincial Government of Dinagat Islands
Barangay Cuarinta, San Jose, Dinagat Islands
November 24, 2022 – March 28, 2024
Scope of Work
● Design and Build Services

Construction of Provincial Tourism, Culture and Heritage Center
Provincial Government of Dinagat Islands
Barangay Cuarinta, San Jose, Dinagat Islands
February 7, 2025 – Present
Scope of Work
● Build Services
Learn More

Mining and Quarry

Aggregates Production